Sparks City Council Meeting 10/22/2012 2:00:00 PM
Monday, October 22, 2012 2:00 PMSparks Legislative Building, 745 E. 4th Street, Sparks, NV 89431
General Business: 6.4
Title: Consideration and possible approval of a contract for the North Truckee Drain – Kiley Ranch South Reach Realignment Project, Bid Number 12/13-003, PWP WA-2012-368 to Reno Tahoe Construction, Inc. in the amount of $447,701.30.
Petitioner/Presenter: John A. Martini, P.E., Assistant Director of Community Services/Andrew Hummel, P.E., Utility Manager
Recommendation: Staff recommends that the City Council award the North Truckee Drain – Kiley Ranch South Reach Realignment Project, Bid Number 12/13-003, PWP WA-2012-368 to Reno Tahoe Construction, Inc. in the amount of $447,701.30
Financial Impact: $300,000 is available for the North Truckee Drain – Kiley Ranch South Reach Realignment Project FY 12/13 in CIP #136808. Additional budget of $147,701.30 will be moved from Storm Drain System & Ditch Rehab (CIP# 136803, Program 13-6803) to 13-6808 to offset the shortfall. Construction expenses will post to Account 604130, Program 13-6808.
Total Costs: $447,701.30
Total Costs: $447,701.30
Fund: Storm Drains Cap Proj Fund Account: 604130 Program: NTD/Kiley Ranch South Reach Improvement Project (13-6808) Amount: $447,701.30 Budget Status: Budget Exists |
Business Impact (Per NRS 237):
A Business Impact Statement is not required because this is not a rule.
A Business Impact Statement is not required because this is not a rule.
Agenda Item Brief: Consideration and possible award of the North Truckee Drain – Kiley Ranch South Reach Realignment Project to Reno Tahoe Construction, Inc. in the amount of $447,701.30. The project consists of clearing obstructions to the channel’s conveyance and restoration of wetlands vegetation.
Background: The purpose of the North Truckee Drain – Kiley Ranch South Reach Realignment Project is to perform wetlands rehabilitation activities in the North Truckee Drain, from Tree Swallow Lane to Los Altos Parkway. The channel is filled with excess vegetation and other obstructions, reducing the channel’s conveyance capacity. This project is intended to remove accumulated sediment and restore wetlands vegetation. Restoration of wetlands vegetation is being done as mitigation for the future North Truckee Drain Realignment Project, located in the industrial area of Sparks, closer to the confluence with the Truckee River. This project shall consist of clearing and grubbing, excavation and fill of specified areas; cutting a low-flow channel; removal of an existing sewer line and replacing it at a new grade; planting and creating a wetland habitat as well as appurtenant work as necessary. The Engineer’s Estimate for the improvements is $448,000.00.
Analysis: The project advertised in the Reno Gazette Journal on August 29, 2012 and copies were distributed to local plan rooms. Five bids were opened at city hall on September 27, 2012 at 2:00 P.M. Bid results ranged in cost from $447,701.30 to $897,007.00. Below is a recap of the bids: • Reno Tahoe Construction $447,701.30 • Peavine Construction $455,442.60 • A & K Earthmovers $572,000.00 • Granite Construction $599,599.00 • Sierra Nevada Construction $897,007.00
Alternatives: 1. City Council could award the North Truckee Drain – Kiley Ranch South Reach Realignment Project as outlined by Staff. 2. City Council could reject the North Truckee Drain – Kiley Ranch South Reach Realignment Project and provide direction to the City Manager.
Recommended Motion: I move to award the North Truckee Drain – Kiley Ranch South Reach Realignment Project, Bid Number 12/13-003, PWP WA-2012-368 to Reno Tahoe Construction, Inc. in the amount of $447,701.30.
Attached Files:
Bid Re-cap-North Truckee Drain Kiley Ranch- Bid 12-13-003.pdf
NTD - Kiley CC Exhibit.pdf
RTC Contract-NTD Kiley Ranch.pdf