Sparks City Council Meeting 3/22/2021 2:00:00 PM

Meeting Link: https://zoom.us/j/99404947145
Meeting Dial-in #: 1-669-900-6833 Meeting ID: 994 0494 7145

General Business: 9.6

Title: Consideration, discussion, and possible approval of a construction contract (AC-5739) for the City Hall Remodel Project Bid No. 20/21-008, PWP #WA-2021-135 with Group West Construction, Inc., in the amount of $335,892.00.
Petitioner/Presenter: John Martini, P.E., Assistant City Manager/Brian Cason, P.E.,S.E., Capital Projects Manager
Recommendation: Staff recommends City Council approve the construction contract with Group West Construction, Inc.
Financial Impact: The bid items will be charged to separate CIP Projects in Fund 1404 Capital Projects Fund.
Total Costs: $335,892.00
Fund: Development Services Fund    Account: 604050
Program: 2201 Capital Improvements- Remodel Existing Clerk's Office to Accommodate Bldg Dept. (19-2501)
Amount: $241,400.00    Budget Status: Over Budget (See Budget Correction Plan)
Fund: Capital Projects    Account: 604050
Program: 1404 City Facilities - City Hall Finance Restroom ADA Upgrade (20-1009)
Amount: $48,501.00    Budget Status: Over Budget (See Budget Correction Plan)
Fund: Capital Projects    Account: 604050
Program: 1404 City Facilities - City Hall IT Remodel (20-1006)
Amount: $45,991.00    Budget Status: Over Budget (See Budget Correction Plan)
Budget Correction Plan:
Budget for programs 19-2501, 20-1009, 20-1006 were all approved in FY20, they are all pending CIP Augmentation for FY21, which will be brought to Council at a later date.
Business Impact (Per NRS 237):
    
A Business Impact Statement is not required because this is not a rule.
Agenda Item Brief:

This project includes multiple remodels throughout City Hall that will benefit staff with improved efficiency and additional space along with providing another ADA-accessible restroom and a water bottle filling station.  The project includes a new customer service counter, new mailroom, additional customer service staff space, remodeled office for payroll staff, remodeled restroom in the finance area, and a remodeled IT office area.  Staff recommends approval of the attached construction contract with Group West Construction, Inc., in the amount of $335,892.



Background:

Sparks City Hall was originally constructed in 1969 and has undergone multiple expansions and additions throughout the years.  In 1979, an additional building was constructed that includes the current main entrance, City Manager’s office, City Clerk’s Office, and Human Resources area, along with a basement area.  The basement consists of a mechanical and electrical room, conference and training room space, restrooms, staff offices, and storage areas. As paper documents have been converted to digital media, this has freed up storage space that would be better suited for office use. The project utilizes each space more effectively. There are also several offices in the payroll, finance, and information technology (IT) areas that were originally constructed for individual use and would use space more efficiently if joined together. Lastly, the restrooms in the finance area do not meet current ADA standards and are outdated.  This project will expand the restrooms to meet current ADA requirements. 



Analysis:
This project was advertised on January 20, 2021, and two addenda were issued during the formal bid process.  Six (6) bids were received at City Hall on February 17, 2021, as a result of the formal bid process.  A summary of those bids is attached for City Council's review, and the total bid amounts are as follows:
 
Engineers Estimate $475,000.00
Group West Construction, Inc. $335,892.00
Bruce Purves Construction, Inc. $337,361.00
Reyman Brothers Construction, Inc. $361,097.80
Truckee Meadows Construction $378.600.00
J & S Custom Homes, Inc. $404,612.00
Norman Ventures NV, Inc. $425,302.00

Staff recommends City Council award the contract to the lowest responsive bidder, Group West Construction, Inc., which submitted a bid in the amount of $335,892. This bid includes a force account of $50,000.  The construction contract for the project has been attached for reference.

 



Alternatives:
  1. City Council may approve the construction contract as outlined by staff.
  2. City Council may reject the construction contract and provide direction to the City Manager.


Recommended Motion:

I move to approve construction contract (AC-5739) for the City Hall Remodel Project with Group West Construction, Inc., in the amount of $335,892.00.  



Attached Files:
     01 - City Hall Remodel Area Map.pdf
     02 - City Hall Remodel Full Bid Recap.pdf
     03 - City Hall Remodel Project Group West Contract.pdf