Sparks City Council Meeting 1/27/2020 2:00:00 PM
Monday, January 27, 2020 2:00 PMCouncil Chambers, Legislative Bldg, 745 4th Street, Sparks, NV
General Business: 9.4
Total Costs: $847,007.00
Fund: Road Fund Account: 603190 Program: 1401 - Pavement Mgmt Prog - Street Improvements - Corr & Rehab (20-0500) Amount: $397,107.46 Budget Status: Budget Exists |
Fund: Road Fund Account: 604120 Program: 1401 - Pavement Mgmt Prog - Sidewalk Rehab (20-0501) Amount: $189,417.22 Budget Status: Budget Exists |
Fund: Sanitary Sewer Cap Proj Fund Account: 604150 Program: Annual Sewer System Street Improvement Coordination (20-6596) Amount: $19,268.73 Budget Status: Budget Exists |
Fund: Storm Drains Cap Proj Fund Account: 604150 Program: Annual Storm Drain Street Improvment Coordination (20-6690) Amount: $145,713.59 Budget Status: Budget Exists |
Fund: Storm Drains Cap Proj Fund Account: 604120 Program: Annual Curb, Gutter, and Sidewalk Projects (20-6692) Amount: $95,500.00 Budget Status: Budget Exists |
A Business Impact Statement is not required because this is not a rule.
The project involves removing and replacing deteriorating curb gutter, sidewalk, and driveway approaches along with constructing new pedestrian ramps and reconstructing the roadway with new asphalt. Refer to the attached vicinity map for street locations. The project advertised on November 27, 2019. On December 12, 2019, the City of Sparks received five (5) qualified bids for this project on. Sierra Nevada Construction submitted the low bid in the amount of $847,007.
Background:
The 2020 Street Rehabilitation –Unit 2 Project is part of the City’s Transportation System – Pavement Management Program. The project was prioritized through the City’s Pavement Management System and outline in the 5-year Program of Projects.
Analysis:
The project scope identifies the need to remove and replace as needed deteriorating curb gutter, driveway approaches, sidewalk ramps and reconstruct the roadway with new asphalt on the streets highlighted on the attached vicinity map.
The City of Sparks received five (5) qualified bids for this project. Bids were received December 12, 2019 at 1:45pm and opened at 2:00pm.
A bid summary of the qualified bidders is shown below:
Engineer’s Estimate $888,000.00
Sierra Nevada Construction $847,007.00
Spanish Springs Construction $860,444.00
West Coast Paving $892,262.00
Q&D Construction $896,671.50
Granite Construction $974,974.00
The contract is attached for review and discussion.
Alternatives:
- Council could approve the construction contract as outlined by Staff.
- Council could reject the proposed construction contract and provide direction to the City Manager.
Recommended Motion:
I move to approve construction contract (AC-5648) for the 2020 Street Rehabilitation – Unit 2-Tanglewood Drive Neighborhood Project with Sierra Nevada Construction in the amount of $847,007.
Attached Files:
02-2020 Street Rehab Unit 2 - SNC Contract.pdf
01-2020 Street Rehab Unit 2 - Vicinity Map.pdf