Sparks City Council Meeting 1/13/2020 2:00:00 PM

    Monday, January 13, 2020 2:00 PM
    Council Chambers, Legislative Bldg, 745 4th Street, Sparks, NV

General Business: 9.11

Title: Consideration, discussion, and possible approval of the Police Department HVAC Upgrade Phase 1 Project Bid No. 19/20-008, PWP #WA-2020-073 construction contract (AC-5640) with Mesa Energy Systems dba Emcor Services Nevada in the amount of $494,947.
Petitioner/Presenter: John Martini, P.E., Assistant City Manager/Brian Cason, P.E., S.E., Capital Projects Manager
Recommendation: Staff recommends City Council approve the construction contract with Mesa Energy Systems dba Emcor Services Nevada.
Financial Impact: $494,947.00 will be funded out of Fund 1404 capital Projects Fund, CIP Programs 17-002 and 19-1008
Total Costs: $494,947.00
Fund: Capital Projects    Account: 604050
Program: 1404 City Facilities - Police Dept HVAC System Retrofit (17-1002)
Amount: $404,947.00    Budget Status: Over Budget (See Budget Correction Plan)
Fund: Capital Projects    Account: 604070
Program: 1404 City Facilities - Police Dept. - Liebert HVAC Unit in Server Room (19-1008)
Amount: $90,000.00    Budget Status: Over Budget (See Budget Correction Plan)
Budget Correction Plan:
Funds are currently available in both programs in their respective fiscal year.
Business Impact (Per NRS 237):
    
A Business Impact Statement is not required because this is not a rule.
Agenda Item Brief:

This project is the first phase of HVAC upgrades to the Sparks Police Department building.  The upgrades in this phase include the replacement of high maintenance fan coil units with new variable air units that provide the facility with improved control and efficiency.  A new Liebert HVAC Unit will also be installed in the Computer Server Room to ensure the protection of Police Department electronic data.  Staff recommends approval of the attached construction contract with Mesa Energy Systems dba Emcor Services Nevada in the amount of $494,947.



Background:

The Police Department at 1701 East Prater Way was originally constructed in 1991.  This facility provides space for all police department staff and operates 24 hours a day, 7 days a week.  The existing HVAC system is 28 years old and nearing the end of its useful life and in need of replacement.  Phase 1 includes the replacement of high maintenance fan coil units with new variable air units that provide improved control and efficiency, along with a new Liebert HVAC System installed to protect electronic data stored in the computer server room of the Police Department.  The new variable air units control the air supplied to each office within the facility with multiple units located on each floor.  Phase 2 is included in the five-year Capital Improvement Plan and includes the replacement of the boiler and chiller to complete the HVAC System replacement.  The system is showing its age with an increase in maintenance costs and decrease in efficiency over recent years. 



Analysis:

The project was advertised on November 20, 2019 and one addendum was issued during the formal bid process.  Five (5) bids were received at City Hall on December 17, 2019 as a result of the formal bid process.  A full recap is attached for your review.  Staff recommends award to the low responsive bid submitted by Mesa Energy Systems dba Emcor Services Nevada, in the amount of $494,947, which includes a force account of $25,000.  The construction contract for the project has been attached for reference.  A bid summary of the responsive bidders is shown below for your review: 

Engineers Estimate $495,000.00
Mesa Energy Systems dba Emcor Services Nevada $494,947.00
Ryan Mechanical $683,750.00
D&D Plumbing, Inc. $701,190.00
RHP Mechanical Systems $751,656.00
Mt. Rose Heating & Air Conditioning $772,000.00

 



Alternatives:
  1. Council could approve the construction contract as outlined by Staff.
  2. Council could reject the construction contract and provide direction to the City Manager.


Recommended Motion:

I move to approve construction contract (AC-5640) for the Police Department HVAC Upgrade Phase 1 Project with Mesa Energy Systems dba Emcor Services Nevada in the amount of $494,947.  