Sparks City Council Meeting 1/14/2019 2:00:00 PM

    Monday, January 14, 2019 2:00 PM
    Council Chambers, Legislative Building, 745 4th Street, Sparks, NV

General Business: 9.11

Title: Consideration, discussion, and possible approval of an Interlocal Cooperative Agreement (ICA)(AC-5544) with the Regional Transportation Commission (RTC) of Washoe County for the Signal Timing 5-Phase 3 Project including reimbursement to the City of Sparks for up to $25,000.
Petitioner/Presenter: John Martini, P.E., Community Services Director/Amber Sosa P.E., Transportation Manager
Recommendation: Staff recommends the City Council approve the Interlocal Cooperative Agreement.
Financial Impact: N/A
Business Impact (Per NRS 237):
    
A Business Impact Statement is not required because this is not a rule.
Agenda Item Brief:

This Interlocal Cooperative Agreement (ICA) is to allow the City of Sparks staff to assist the RTC in implementing new signal timing on a reimbursement basis.  



Background:

See Analysis.



Analysis:

The City of Sparks will provide staff to assist the RTC in implementing new signal timing into the City of Sparks central traffic system.  The Interlocal Cooperative Agreement (ICA) allows the RTC to reimburse the City of Sparks up to $25,000 of the City’s staff time.  The funding for the project is 95% reimbursable from the Nevada Department of Transportation (NDOT) utilizing Congestion Mitigation Air Quality (CMAQ) funds. 

The ICA is attached to the staff report for review and discussion.



Alternatives:
  1. City Council could approve the Interlocal Cooperative Agreement as outlined by Staff.
  2. City Council could reject the Interlocal Cooperative Agreement and provide direction to the City Manager.


Recommended Motion:

I move to approve the Interlocal Cooperative Agreement with the Regional Transportation Commission for the Signal Timing 5 – Phase 3 Project