Sparks City Council Meeting 4/27/2015 2:00:00 PM
Monday, April 27, 2015 2:00 PMCouncil Chambers, Legislative Bldg, 745 4th St., Sparks
General Business: 9.2
Total Costs: $891,444.00
Fund: Road Fund Account: 604140 Program: 1401 - Pavement Mgmt Prog - Street Improve - 2015 Street Rehab Unit 3 (15-0500C) Amount: $715,756.00 Budget Status: Budget Exists |
Fund: Road Fund Account: 604120 Program: 1401 - Pavement Mgmt Prog - Sidewalk Rehab - 2015 Street Rehab Unit 3 (15-0501C) Amount: $35,948.00 Budget Status: Budget Exists |
Fund: Storm Drains Cap Proj Fund Account: 604130 Program: Annual Storm Drain Street Improvment - 2015 Street Rehab Unit 3 (15-6690E) Amount: $121,740.00 Budget Status: Budget Exists |
Fund: Sanitary Sewer Operations Fund Account: 603190 Program: Annual Sewer System Street Improvement - 2015 Street Rehab Unit 3 (15-6593D) Amount: $18,000.00 Budget Status: Budget Exists |
A Business Impact Statement is not required because this is not a rule.
Consideration and possible award of the 2015 Street Rehabilitation – Unit 3, Bid No. 14/15-013, PWP-WA-2015-112 to Spanish Springs Construction, in the amount of $891,444. Staff recommends that council award the contract.
Background:
This 2015 Street Rehabilitation Unit 3 project is part of the City’s Transportation System - Pavement Management Program. The project was prioritized through the City’s Pavement Management System and outlined in the 5 year Program of Projects.
Analysis:
The project scope identifies the need to remove and replace as needed rundown curb gutter, driveway approaches, sidewalk ramps and reconstruct the roadway with new asphalt on Sycamore Glen Drive from Springland Drive to Figoni Ranch Road, Sorensen Way from Baring Boulevard to Del Rosa Way and Del Rosa Way from Sorensen Way to Blossom View Drive.
The City of Sparks received three (3) qualified bids for this project, which were received March 25, 2015 at 1:45 p.m. and opened on March 25, 2015 at 2:00 p.m.
A bid summary of the qualified bidders is shown below:
- Engineers Estimate $950,000
- Spanish Springs Construction $891,444
- Sierra Nevada Construction $942,007
- Granite Construction $992,992
Alternatives:
- City Council could award the project as outlined by Staff.
- City Council could reject the proposed project and provide direction to the City Manager.
Recommended Motion:
I move to award the 2015 Street Rehabilitation– Unit 3, to Spanish Springs Construction, in the amount of $891,444.