Sparks City Council Meeting 5/13/2019 2:00:00 PM
Monday, May 13, 2019 2:00 PMCouncil Chambers, Legislative Bldg, 745 4th Street, Sparks, NV
General Business: 9.3
Total Costs: $230,000.00
Fund: Storm Drains Operations Fund Account: 604130 Program: 15th St SD Repair RTC (19-6696A) Amount: $88,000.00 Budget Status: Over Budget (See Budget Correction Plan) |
Fund: Sanitary Sewer Cap Proj Fund Account: 604150 Program: El Rancho Pavement Coordination and C St Sewer Repair RTC (19-6586A) Amount: $142,000.00 Budget Status: Over Budget (See Budget Correction Plan) |
Budget Correction Plan: $87,068 from Acct 603190 Program 19-6696 was recently moved to Acct 604130/19-6696A “15th St SD Repair RTC” $124,000 from Acct 604150 Program 19-6586 was recently moved to Acct 604150/19-6586A “El Rancho Pavement Coordination and C St Sewer Repair RTC” |
A Business Impact Statement is not required because this is not a rule.
The City of Sparks works together with the RTC on the rehabilitation of regional roads. The RTC’s rehabilitation project for FY19, the Sparks Consolidated 2019 Project, includes roadways that also need some rehabilitation for portions of the City’s underground utilities, sewer and storm drain. This interlocal cooperative agreement for reimbursement will allow the City’s underground utility rehabilitation needs to be included in the construction of RTC’s roadway project, providing for efficiency and effectiveness.
Background:
The RTC annually works on their Regional Pavement Preservation Program. The program identifies the specific needs for regional road maintenance throughout the Truckee Meadows. The City of Sparks Pavement Quality Team and Utility Division work very closely with the RTC to prioritize regional road projects in the City of Sparks. Included in the RTC’s FY2019 Program, under the Sparks Consolidated 2019 Project are 15th Street, from C Street to Prater, Franklin Way from the railroad tracks to E Greg Street, and Hulda Ct. Analysis from the City of Sparks’ Utility Division showed that some portions of underground facilities, sewer and storm drain lines, within the limits of the RTC’s roadway project are in need of rehabilitation.
Analysis:
In the interest of rehabilitating the underground utilities before the roadway is reconstructed, City of Sparks staff has worked with RTC staff to include the construction of the underground needs into the RTC’s roadway project. This interlocal agreement details the reimbursement that will come from the City of Sparks and to the RTC for the cost of construction associated with the underground components, as requested by the City of Sparks for rehabilitation. The engineer’s estimate for the construction work associated with the utility work, requested by the City of Sparks, is approximately $230,000.00. The project will be bid, awarded and managed by the RTC. The project is expected to be constructed in the summer of 2019. The RTC and the City of Sparks will work together through construction, handling any changes that could come up. The final reimbursement amount will be for the actual cost at the time of construction completion.
The Interlocal Agreement is attached for review and discussion.
Alternatives:
- City Council could approve the Interlocal Agreement as outlined by Staff.
- City Council could reject the Interlocal Agreement and provide direction to the City Manager.
Recommended Motion:
I move to approve the Interlocal Cooperative Agreement (AC-5565) for Reimbursement with the Regional Transportation Commission (RTC), in the amount of $230,000.00, for construction of sewer and storm drain improvements to be included in the RTC’s Sparks Consolidated 2019 Project.