Sparks City Council Meeting 6/12/2017 2:00:00 PM
Monday, June 12, 2017 2:00 PMCouncil Chambers, Legislative Bldg., 745 4th St. , Sparks, NV
General Business: 9.13
Total Costs: $125,300.00
Fund: Sanitary Sewer Operations Fund Account: 603235 Program: Rate Study 5 Year Update (17-6595) Amount: $75,000.00 Budget Status: Budget Exists |
Fund: Effluent Operations Fund Account: 603445 Program: Rate Study 5 Year Update (17-6792) Amount: $25,000.00 Budget Status: Budget Exists |
Fund: Storm Drains Operations Fund Account: 603235 Program: Rate Study 5 Year Update (17-6694) Amount: $25,300.00 Budget Status: Budget Exists |
A Business Impact Statement is not required because this is not a rule.
Consideration and possible approval of a contract for a Sewer, Storm Drain, and Effluent Systems Rate Study Analysis, with Farr West Engineering, in the amount of $125,300. The Rate Study Analysis will evaluate and recommend changes to the City’s Utility rates, policies, and ordinances based on economic changes since the last utility rates update in 2012. Staff recommends approval.
Background:
A Rate Study, covering sanitary sewer, storm drain, and effluent systems, was completed in 2008 and subsequently updated in 2012. The economic climate has changed since 2012, affecting residential and commercial development as well as existing users. Completion of the 2016 City of Sparks Sanitary Sewer Master Plan identified significant Capital Investments required within the sanitary sewer infrastructure. These changes have prompted a detailed analysis of the Utility Rates, Policy, and Code.
Farr West Engineering was selected by staff to perform the Rate Study due to their experience with similar studies and their knowledge of regional issues relating to the City of Sparks. The scope of services is attached for Council’s review.
Analysis:
The proposal provided by Farr West Engineering provides the services needed to evaluate and recommend changes for the City’s Utility rates, policies, and ordinances. The Rate Study Proposal fee is $125,300 and is scheduled to be completed within nine months.
Alternatives:
1. City Council could approve the contract as outlined by Staff.
2. City Council could reject the contract and provide direction to the City Manager.
Recommended Motion:
I move to approve a contract for a Sewer, Storm Drain, and Effluent Systems Rate Study Analysis, with Farr West Engineering, in the amount of $125,300.
Attached Files:
Farr West Rate Study Proposal.pdf
Farr West Contract-Rate Study Analysis Contract.pdf