Sparks City Council Meeting 8/8/2016 2:00:00 PM

    Monday, August 8, 2016 2:00 PM
    Council Chambers, Legislative Building, 745 Fourth Street, Sparks, NV

Consent Items: 8.3

Title: Consideration and possible approval of a reimbursement to the City of Reno for Sparks’ share of a contract (AC-5274) with KG Walters Construction for the 2016 Clarifier Rehabilitation Project at the Truckee Meadows Water Reclamation Facility (TMWRF) not to exceed $123,974.24.
Petitioner/Presenter: John A. Martini, P.E. – Community Services Director/Michael Drinkwater, P.E. – TMWRF Plant Manager
Recommendation: Staff recommends City Council approve Sparks’ share of the contract between the City of Reno and KG Walters Construction Inc, for the TMWRF Primary and Secondary 1C Clarifiers 2016 Rehabilitation Project.
Financial Impact: There is no impact to the General Fund. Year One, FY 2016-2017, of the approved 5-year Capital Improvement Plan (CIP) for the City of Sparks included $3,709,502.50 for Sparks’ share of TMWRF Joint Capital Projects. Of those projects the next phase of the Clarifier Basin Concrete & Steel Rehabilitation was planned. In addition, Finance will bring forward to FY17 $77,013.35 of remaining appropriations to fully fund the cost of rehabbing Primary & Secondary Clarifiers 1C. The City of Reno will enter into a construction contract with KG Walters, Inc. in an amount of up to $395,200.00 and will administer the project. Reimbursement will be sought from the City of Sparks for its share of expenses through the current cost sharing agreement for TMWRF capital projects, based on ownership of TMWRF, outlined in Table 1. Expenses will post to account 603190, Maintenance and Repairs, using CIP 16-6590C, TMWRF Clarifier Basins 1C Rehabilitation Project, effecting Fund 1631, Sanitary Sewer Operating Fund.
Total Costs: $123,974.24
Fund: Sanitary Sewer Cap Proj Fund    Account: 604090
Program: FY16 TMWRF Projects (16-6590)
Amount: $123,974.24    Budget Status: Budget Exists
Business Impact (Per NRS 237):
    
A Business Impact Statement is not required because this is not a rule.
Agenda Item Brief:

TMWRF staff is asking the City Council to approve reimbursement to the City of Reno for Sparks’ share of a contract between Reno and KG Walters Construction Inc, for the TMWRF Primary and Secondary 1C Clarifiers 2016 Rehabilitation Project, in an amount not to exceed $123,974.24.



Background:

TMWRF utilizes 14 primary and secondary clarifiers in the wastewater treatment process.  These clarifiers are concrete tanks with steel mechanical rotating mechanisms and they range from 16 to 50 years old.  Over years of continuous operation, the concrete tank structures and mechanical equipment require repairs and rehabilitation.  Annual repair and rehabilitation of the clarifier basins is included in the Joint Coordinating Committee approved TMWRF Capital Improvement Program.  For the 2016 clarifier rehabilitation project the Primary and Secondary 1C Clarifier Basins were selected. 

The rehabilitation activities consist of repair of expansion joints, replacement of the steel roller wear ring, providing minor repairs to the grout beds, concrete walls and some portions of the steel hardware.  This work is considered necessary to prevent further deterioration of aging concrete structural components, which if not addressed could result in the need to replace the structure.



Analysis:

The City of Reno held an open, competitive bid to select the proposed contractor.  KG Walters Construction, Inc. was the lowest responsible bidder with a total project bid of $395,200.00.  Reno will continue to administer the contract and will be reimbursed for a portion of the costs by the City of Sparks through the Sparks – Reno cost sharing agreement for TMWRF.  The City of Reno and the City of Sparks share the cost for this project based upon their ownership of TMWRF, which is 68.63% for Reno and 31.37% for Sparks. Based on the ownership percentages, Sparks’ share of this agreement is up to $123,974.24.  The cost split between Reno and Sparks is shown in Table 1, attached.



Alternatives:

Council could direct the manager to have staff provide other alternatives.



Recommended Motion:

I move to approve the reimbursement to the City of Reno for the Sparks’ share of the construction of the Clarifier Rehabilitation Project at TMWRF not to exceed $123,974.24.



Attached Files:
     Table 1.pdf
     City of Reno Staff Report - Clarifier Rehab.pdf
     Clarifier Bid Docs and Contract.pdf
Previous Item
Next Item
Return To Meeting